5 Dec 2016, 3:05 pm by Thomas G. Heintzman
Thus, in the CCDC-2 Stipulated Price Contract, the main notice/claims provisions are as follows: 6.4.1. [read post]
23 Oct 2016, 8:08 am by Thomas G. Heintzman
“Standard form” construction contracts, such as the CCDC contracts prepared by the Canadian Construction Document Committee, are not prepared by one party or one side of the industry and presented to the other on a “take it or leave it” basis. [read post]
20 Sep 2016, 6:57 am by USPTO
As part of our Enhanced Patent Quality Initiative, the goal of the CCDC is an improved data capture system to enable all reviewers of finished work products to consistently document and access quality review data in one place. [read post]
20 Sep 2016, 6:57 am by USPTO
As part of our Enhanced Patent Quality Initiative, the goal of the CCDC is an improved data capture system to enable all reviewers of finished work products to consistently document and access quality review data in one place. [read post]
14 Jun 2016, 6:55 am by Thomas G. Heintzman
Thus the CCDC contracts which are often used between owners and contracts appear to fall within the sort of standard form contracts that the Court of Appeal was discussing. [read post]
4 Mar 2016, 8:58 am by Thomas G. Heintzman
Thus, GC 8.2.6 of the CCDC 2 Stipulated Price Contract says that, after certain preliminaries including notice and mediation, “either party may refer the dispute to be finally resolved by arbitration…. [read post]
8 Dec 2014, 10:29 am by Jason Weiner
Unlike most other jails, the CCDC also accepts bail of up to $3,000 by VISA or Mastercard. [read post]
5 Sep 2014, 3:29 pm by Cicely Wilson
In 2009, CCDC notified Abercrombie that Hollister stores at two malls in Colorado violated the ADA. [read post]
5 Sep 2014, 7:40 am by Allison Tussey
Marshals Office on August 26, 2014, at an apartment building in Las Vegas, Nev. and was booked into the Clark County Detention Center (CCDC). [read post]
21 Sep 2013, 2:59 pm by Thomas G. Heintzman
The standard form CCDC bond says:   “…A Claimant for the purpose of this Bond is defined as one having a direct contract with the Principal for labour, material, or both, used or reasonably required for use in the performance of the Contract…. [read post]
9 Jun 2013, 8:36 am by Thomas G. Heintzman
How does this decision affect the interpretation of GC 8.2 of the CCDC 2 Stipulated Price Contract? [read post]
20 Apr 2013, 3:02 pm by Thomas G. Heintzman
For example, GC 8.2 of the CCDC 2 Stipulated Price Contract is the dispute resolution clause in that contract. [read post]
30 Mar 2013, 2:34 pm by Thomas G. Heintzman
”  For example, Article 10.1 of the CCDC Cost Plus Contract states that the contract “shall enure to the benefit of and be binding on…successors”. [read post]
28 Aug 2012, 5:54 am by Thomas Heintzman
 Then, on January 20, 2006, counsel for Constance Lake suggested that the parties dispense with the provisions under their contract and proceed directly with arbitration under an amended form of the CCDC 40 Rules for Arbitration of Construction Disputes. [read post]
28 Aug 2012, 5:33 am by Thomas G. Heintzman
 Then, on January 20, 2006, counsel for Constance Lake suggested that the parties dispense with the provisions under their contract and proceed directly with arbitration under an amended form of the CCDC 40 Rules for Arbitration of Construction Disputes. [read post]
24 Jul 2012, 1:24 pm by Thomas G. Heintzman
Thus, (a)  Liquidated Damages: A liquidated damages clause in the main contract was not incorporated by reference into the sub-contract.10 A bond which contained a clause incorporating the building contract between the owner and the contractor was held not to impose on the surety the obligation to pay the liquidated damages referred to in the building contract between the owner and the contractor.11 (b)  Lien Security:  The obligation to post security for lien claims contained in… [read post]