Part of NIPSCO’s TDSIC plan included certain system deliverability projects, specifically NIPCO’s need to upgrade its Marktown substation and improve the distribution and transmission related system deliverability in the Nappanee area. [read post]
27 May 2014, 1:32 pm
If you think you may be affected by the NIPSCO's Greentown-Reynolds Electric System Improvement Project and/or are interested in a free consultation, contact our eminent domain landowner attorneys at 1-888-318-3761 or visit us on the web at www.landownerattorneys.com. [read post]
19 Jul 2007, 8:46 am
In this entry yesterday, the ILB quoted from a NWI Times story that:The state's top environmental regulator has told NIPSCO it will be subject to the U.S. [read post]
At issue in this case was a seven-year plan filed by the Northern Indiana Public Service Company (“NIPSCO”) seeking approval for an improvement to its gas system under the TDSIC statute from the IURC. [read post]
2 Jun 2014, 1:03 pm
Titled the Greentown-Reynolds project, it will ultimately connect Duke Energy’s Greentown substation east of Kokomo to NIPSCO’s substation in Reynolds. [read post]
A summary of that case can be found here: https://www.indianabusinesslawyerblog.com/nipsco-industrial-group-v-northern-indiana-public-service-co-100-n-e-3d-234-ind-2018/. [read post]
2 Jun 2014, 1:00 pm
Titled the Greentown-Reynolds project, it will ultimately connect Duke Energy’s Greentown substation east of Kokomo to NIPSCO’s substation in Reynolds. [read post]
2 Jul 2014, 8:28 am
Titled the Greentown-Reynolds project, it will ultimately connect Duke Energy’s Greentown substation east of Kokomo to NIPSCO’s substation in Reynolds. [read post]
4 Jul 2007, 6:26 am
The first one, from Oct. 17, 2004, quoted a story in the Fort Wayne Journal Gazette that began:A NIPSCO worker trying to remove a gas meter for non-payment discovered a mountain of rusting industrial barrels filling the site of a defunct recycling firm. [read post]
22 Dec 2006, 8:54 pm
NIPSCO raises two related issues, which we restate as: 1) whether the IURC exceeded its statutory authority by requiring NIPSCO to make a direct cash payment of 2.5 million dollars to Jupiter for the purchase of equipment that will benefit Jupiter and that Jupiter will own; and 2) whether the IURC exceeded its statutory authority by prohibiting NIPSCO from recovering the 2.5 million dollars in rates. [read post]
18 Jul 2007, 2:22 pm
Mitchell power plant in Gary:The state's top environmental regulator has told NIPSCO it will be subject to the U.S. [read post]
25 Jun 2009, 11:32 am
  A dispute arose when NIPSCO asserted that the price adjustment applied both to the Energy Charge (a fixed number of hours of use each month under the agreement) and the Demand Charge (for energy use beyond that fixed number). [read post]
14 Jan 2011, 7:10 am by Marcia Oddi
Gitte Laasby of the Gary Post Tribune reported: From a story headed "Disputed electric rate hike dropped: Utility to pursue... [read post]
12 Feb 2010, 7:30 am by Alan Ackerman
Indiana Gasification, which planned to sell gas to Merrillville-based NIPSCO and Evansville-based Vectren, shelved plans in late-2008 after failing to reach long-term gas supply contracts with utilities, which feared such contracts could impair their long-term credit. [read post]